Question

    A can complete 40% of a work in 6 days and B can complete 33(1/3)% of the same work in 8 days. They work together for 8 days. C alone completes the remaining work in 4 days. A and C together will complete the same work in:

    A 13(1/8) days Correct Answer Incorrect Answer
    B 12 days Correct Answer Incorrect Answer
    C 9 days Correct Answer Incorrect Answer
    D 10 days Correct Answer Incorrect Answer

    Solution

    The correct answer is D

    Practice Next

    Relevant for Exams: