The series is alternated with two series: IDF, NIK I + 5 = N D + 5 = I F + 5 = K NIK,? N + 4 = R I + 4 = M K + 4 = O RMO, UPR R + 3 = U M + 3 = P O + 3 = R UPR, WRT U + 2 = W P + 2 = R R + 2 = T VQS, WRT V + 1 = W Q + 1 = R S + 1 = T
X can do a piece of work in 25 days. He worked at it for 10 days and then Y finished it in 24 days. In how many days can X and Y together finish the wor...
Ajay, Bablu and Chirag can complete a certain work in 21, 28 and 15 days respectively. Ajay and Chirag started the work while Bablu joined them after ...
'Sita' can complete some work alone in 20 days. 'Geeta' is twice as efficient as 'Reeta' and three times as efficient as 'Sita'. If 'Sita' and 'Reeta' s...
A can finish a task in 32 days, while B can complete the same task 8 days sooner than A. If they together earn a total of Rs. 1050 for the job, how much...
'Manoj' can complete some work alone in 40 days. 'Sohan' is twice as efficient as 'Rohan' and five times as efficient as 'Manoj'. If 'Manoj' and 'Rohan'...
M and N, working in tandem, can successfully attain the sales target within a span of 15 days. Now, if N's efficiency is _______ percent less than that ...
A work can be completed by ‘A’ and ‘B’, alone in 15 days and 20 days, respectively. Find the number of days taken by ‘C’ to complete the sam...
‘A’ and ‘B’ alone can do a certain work in 30 days and 40 days, respectively. Both started the work together but after ‘x’ days ‘A’ left...
A buffalo alone can plough field ‘A’ in 50 days. A Bull alone can plough the field ‘A’ in 75 days. Find the number of days taken by 1 bulls and ...
28 men can complete a work in 20 days. 40 women can complete the same work in 28 days. 20 men and 12 women started working and after 16 days, 20 more wo...