Let the number = 'x'According to the question,(x2 - 26x) + 169 = 0Or, x2 - 13x - 13x + 169 = 0Or, x(x - 13) - 13(x - 13) = 0Or, (x - 13)(x - 13) = 0So, the required number 'x' = 13
A and B together, B and C together and A and C together can complete a piece of work in 10 days, 14 days and 18 days respectively. Find the ratio...
4 girls working together for 1 day complete the same amount of work as 6 men working together for 1 day. The efficiency of 1 man ...
A certain number of men, represented as 'm', can finish a task in 40 days. However, if there were 15 additional men, the same task would be completed in...
Thirty men working 8 hours daily complete a task in 16 days. If the work increases to three times the original and needs to be fi...
A, B, and C can complete a task individually in 45, 35, and 63 days respectively. They start working together, but A leaves 24 days before the work is c...
Puneet and Qureshi together can complete (7/8)th of a piece of work in 9 days, Qureshi and Rohit together can complete (3/5)th of the work in 8 days and...
A, B and C alone can complete a work in 24, 48 and 32 days respectively. All of them started working together but after 2 days from start A left the job...
A team of 40 men is assigned to finish a project within 24 days. They began the task simultaneously. To complete the project 6 days ahead of the planned...
A tank is filled by three pipes with uniform flow. The first two pipes operating simultaneously fill the tank in the same time during which the tank is ...
150 unit of work can be completed by P alone in 25 days. P started working alone and joined by Q after 15 days such that they completed the remaining wo...