School-vx All-ab Our-mi These-ey Friends-cn Markets-ra From-ho Bought-kd
X can do a piece of work in 20 days. He worked at it for 5 days and then Y finished it in 15 days. In how many days can X and Y together finish the work?
Ankit and Priya together can complete a piece of work in 200 days and 10 minutes, while Priya and Vikas together can complete the same work in 130 days ...
Sam and John can complete a piece of work in 8 days and 12 days respectively. They work together but after 2 days, Sam leaves. John finishes the remaini...
A can complete a task 40% more efficiently in 25 days, whereas B, with a 25% efficiency boost, can finish the same task in 21 days. They collaborated at...
138 unit of work can be completed by P alone in 23 days. P started working alone and joined by Q after 11 days such that they completed the remaining wo...
'Zara' is capable of finishing a specific task in 60 days. On the other hand, 'Armaan' takes 40% more time than 'Zara' to complete the same task, while ...
Ram can do a work in 60 days while Mohan can do the same in 84 days. If Ram work for 'x' days while Mohan work for ' x + 2' days then one-third of the w...
Neha can do a work in 45 days while Meha can do the same in 90 days. If Neha works for 'q' days while Meha works for 'q + 2' days then one-sixth of the ...
Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed ...
Amit can complete a task alone in 20 days. Bheema and Chetna, working together, can complete the same task in 12 days. The ratio ...