A’ and ‘B’ together can complete a work in 25 days while ‘A’ takes 30 days to complete the same work alone. If ‘C’ is 20% more efficient t...
20 men can do a piece of work in 14 days working 9 hours a day. How many men can do double the work in 16 days working 7 hours a day?
A and B can complete a task together in 18 days, while B alone takes 36 days to finish it. A began working alone and left after ‘x’ days, after whic...
P and Q can complete a work in 28 days and 42 days, respectively. P, Q and R together can complete the work in 14 days. If R get a total wage of Rs. 546...
108 unit of work can be completed by P alone in 18 days. P started working alone and joined by Q after 9 days such that they completed the remaining wor...
(x) men can do some work in 42 days. If 10 more men added then the work would have been completed in 30 days, then in how many days (x+45) men can do th...
The efficiency of P, Q, R, S are in the ratio of 6:5:4:3. If P and R can do a work together in 6 days. Then How many days Q and S will take to complete ...
'C' and 'D' together can complete a work in 40 days. They started working together but after 20 days, 'D' left and remaining work was completed by 'C' a...
A work can be completed by ‘A’ and ‘B’, alone in 14 days and 7 days, respectively. Find the number of days taken by ‘C’ to complete the same...
P and Q together can do a piece of work in 30 days, Q and R together can do it in 20 days. P starts the work and works on it for 5 days, then Q takes it...