All are palindrome number except 11222.
P’s 5 days work is equal to Q’s 6 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 60% of ...
P does one fourth as much work as Q in two third of the time. If together they take 24 days to complete the work, how much time shall Q take to do it?
Consider that 'A' and 'B' were collectively paid Rs. 9,000 for a job. Out of this amount, 'B' received Rs. 3,000. If 'B' can finish this task solo in 48...
P’s 3 days work is equal to Q’s 4 days work. If P and Q together can complete the work in 32 days then how much time Q will take to complete 75% of ...
Three workers P1, P2 and P3 got work from the contractor. In 30 days, ‘P1’ completed 30% of work. ‘P2’ is 20% less efficient tha...
‘A’ and ‘B’ can complete a certain work in 18 days and 10 days, respectively. They started working together and worked till completion of the wo...
Worker 'A' can complete the entire task in 35 hours, and Worker 'B' can complete it in 40 hours, when working individually. If both 'A' and 'B' work tog...
Anupam can do a piece of work in 36 days and Rajveer can do it in 15 days. Diksha can do the same work in (17/18) times the number of days required by b...
'Akshay' alone takes 18 days to finish a work while 'Bhim' alone takes 24 days to finish the same work. If 'Akshay' and 'Bhim' work on alternate days st...
Ram can do a piece of work in 12 days and Shyam can do the same work in 16 days. They both started work together, Ram left 2 days before the completion ...