Question
From the following letters, select the sixth and
fourteenth letters from your right and select the fifth and twentieth letter from your left and form a meaningful word. ABCDEFGHIJKLMNOPQRSTUVWXYZ Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Which of the following options is correct regarding that word?Solution
Given letters: A B C D E F G H I J K L M N O P Q R S T U V W X Y Z 6th  and 14th  letter from the right is U  and M . The  5th  and 20th  letters are E  and T . So, the letters are U, M, E, T. The meaningful word can be formed from U, M, E, T is MUTE . Hence, "M is the first letter of that word" is the correct answer.
Virat can do a piece of work in 30 days and Sachin can do the same work in 45 days. If Virat works for 5 days and got Rs. 2100, and the remaining work w...
A buffalo alone can plough field ‘A’ in 10 days. A Bull alone can plough the field ‘A’ in 16 days. Find the number of days taken by 1 bulls and ...
A and B together can complete a task in 12 days, while B and C together can complete the same task in 15 days. A and C together take 20 days to finish i...
Time taken by A and B together to complete a work is 1 day less than the time taken by B alone to complete the same work. With his half efficiency B can...
‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 20 days. If they work together for the entire time and get paid Rs.140...
138 unit of work can be completed by P alone in 23 days. P started working alone and joined by Q after 11 days such that they completed the remaining wo...
A and B can complete a task together in 24 days, while B alone takes 48 days to finish it. A began working alone and left after ‘x’ days, after whic...
40 men can complete a piece of work in 48 days. ‘x’ men started the work and after 30 days 56 more men joined them so that whole work was finished i...
- 'Amit', 'Ravi', and 'Neha' can finish a piece of work in 66, 99, and 132 days respectively. They all started the work, but Amit left 8 days before the work...
Rahul can complete a work in 12 days and Ayush in 15 days. If they work together for 3 days, then the fraction of work that will be left is: