Which among the following statements is definitely true?
Box T is placed in even numbered position. Four boxes are placed between Box X and Box T. Box T is placed above Box X. Only two boxes are placed between the Box Z and Box V in which Box V is placed below Box Z. Box Z is placed in odd numbered position. Box Z is not placed above Box T. From above statements, Case 1: If Box T is placed at 8 th position and then Box X is placed at 3 rd position. Box Z is placed at 7 th position and Box V is placed at 4 th position. Case 1-S: If Box T is placed at 8 th position and then Box X is placed at 3 rd position. Box Z is placed at 5 th position and Box V is placed at 2 nd position. Case 2: If Box T is placed at 6 th position and then Box X is placed at 1 st position. Box Z is placed at 5 th position and Box V is placed at 2 nd position. Based on the above information, we get the initial table as follows Only one box is placed between the Box Y and Box W in which Box W is placed below Box Y. Box X is not placed above Box S. From above statements, Case 1 &2: Based on the above condition, there is no place for Box Y and Box W at s gap of 1 position. Hence, this case becomes invalid and it can be eliminated. Case 1-S: Based on the above condition, Box Y is placed at 6 th position and Box W is 4 th position. Given, Box X is not placed above Box S. Therefore, Box S is placed at 7 th position and Box U is placed at 1 st position. Thus we get the completed table,
Shivam invested 25000 at 12% p.a. simple interest for ‘x’ months. If at the end of ‘x’ months, he received a total amount of Rs.30000. What is t...
'Ajeet' has an efficiency that is 40% lower than 'Chirag's, where as 'Bittu' is 20% more efficient than 'Chirag'. The time difference between 'Bittu' an...
Akhil and Nikhil together can complete a work in 6 days while Nikhil alone takes 18 days to complete 60% of the work. If the efficiency of Sachin is 25%...
P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work &l...
P can do a piece of work in 10 days, Q can complete double the work in 20 days and R can do the work in 15 days. If all of them together earn Rs. 3200, ...
Vijay can do a piece of work in 16 days and Sanjay can do the same work in 24 days. If Vijay works for 6 days and got Rs. 2700, and the remaining work w...
P and Q can separately finish the work in 15 days and 25 days respectively. They worked together and P left the work, so Q complete the remaining work i...
X men can complete the piece of work in 36 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the v...
A alone can do a piece work in 15 days and the time taken by A alone is 50% more than the time taken by B. They started work together alternatively star...
A certain Sales target was assigned to a team of men to complete in 18 days. But 8 men did not turn up for the target and the rest men complete the sale...