Question
Which of the following box is kept just above box B?
Answer the questions based on the information given below. Eight boxes viz. A, B, C, W, X, Y, Z and Q are placed one above the other in the single stack, but not necessarily in the same order. The lowermost box is numbered 1 and the box above is numbered 2 and so on. The consecutive alphabetically named boxes were not placed adjacent to each other. Three boxes are placed between Q and Z where neither of them is placed at the top and bottommost position. Two boxes are placed between Y and C where box C is placed immediately below box Q. Box A is placed immediately above box X.At least three boxes are there between B and W which is not placed at the bottommost position.Solution
1) Three boxes are placed between Q and Z where neither of them is placed at the top and bottommost position. Two boxes are placed between Y and C where box C is placed immediately below box Q. 2) Box A is placed immediately above box X. At least three boxes are there between B and W which is not placed at the bottommost position. Hence, cases 1 and 2 get eliminated.
A buffalo alone can plough field βAβ in 30 days. A Bull alone can plough the field βAβ in 50 days. Find the number of days taken by 2 bulls and ...
A, B, C can do a piece of work in 11 days, 20 days, and 22 days respectively. If B works daily and is supported by A and C on alternate days beginning w...
Amit and Binod receive Rs.1400 for work of 7 days. If Amit is 4 times efficient than Binod, then find the daily wage received by Binod.
P does one fourth as much work as Q in two third of the time. If together they take 24 days to complete the work, how much time shall Q take to do it?
45 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for ...
If A can complete a job in 15 days and B can complete the same job in 10 days, and they work together for 4 days before A leaves. How many more days wil...
'X' and 'Y' together can complete the work in 24 days. 'Y' alone can complete the work in 40 days. If Z is 33.33% more efficient than X, find the time ...
The efficiency of A, B, C, D are in the ratio of 6 : 5 : 4 : 3. If A and C can do a work together in 6 days. Then How much days B and D will take to com...
P and Q together can complete 75% of a work in 15 days while Q alone takes 40% more time than P and Q together to complete the whole work. Find the time...
X men can complete the piece of work in 36 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the v...