Total number of people in the queue = 90 Position of Ms. Braganza from the right = 23 Position of Ms. Margaret from the left = 28 Thus, number of people between them = 90 – (23 + 28) = 90 – 51 = 39 Hence, the correct answer is (B).
Pawan and Qureshi can complete a task in 12 days, while Pawan and Rishi can finish the same task in 40/3 days. Initially, Pawan a...
A, B and C alone can complete a work in 12, 24 and 20 days respectively. All of them started working together but after 2 days from start A left the job...
A’ and ‘B’ together can complete a work in 10 days while ‘A’ takes 30 days to complete the same work alone. If ‘C’ is 50% more efficient t...
Three workers, A, B, and C, can complete a task in 40 days, 72 days, and 45 days respectively. They start working together, but A leaves 20 days before ...
Ankit, Brijesh, and Chirag can complete a task in 30, 60, and 90 days respectively. They all began the work together, but Ankit left after 6 days, and ...
Aman manages to write 256 pages of a book over a span of 24 days, dedicating 8 hours each day to this task. Meanwhile, Pranav, who is known to be 50% mo...
5 girls can do a piece of work in 9 days, 4 boys can do the same piece of work in 8 days, 6 men do the same piece of work in 2 days and 4 women can do t...
A work can be completed by ‘A’ and ‘B’, alone in 10 days and 15 days, respectively. Find the number of days taken by ‘C’ to complete the sam...
Ratio of the work done by P, Q and R in one day is 7:3:8 respectively. They all together can complete the work in 42 days. Q and R worked on it for 21 d...
'B' is 37.5% more productive than 'A'. Together, they can finish a task in 40 days. How many days would it take for 'A' alone to complete the entire task?