Start learning 50% faster. Sign in nowA can finish the work in 40 days and B in 30 days. They both work together for 5 days and then B leaves. How many days will A take to complete the remai...
A and B can finish a work working on alternate days in 19 days, when A works on the 1st day. Similarly, they can finish the work working on alternate da...
The total age of 'R' and 'D' eight years ago was thirty-six. Four years separate 'R' and 'D' in age. Determine the sum of total age (in years) between '...
A and B can do a work in 21 days, A is (7/4) times as efficient as B. In how many days, A alone can complete the (100/3)% of the work?
A contractor hires 12 workers to complete a project in 20 days. After 8 days, 4 more workers are employed, and the project is completed 2 days earlier. ...
A man on the top of a tower, standing on the sea-shore, finds that a boat coming towards him takes 10 minutes for the angle of depression to change fro...
A mobile plan costs Rs.32 for 6 minutes. What is the approximate cost, rupees, for 4 minutes?
A can do (2/5) of a work in 6 days and B can do 30% of the same work in 3 days. They worked together for 4 days. The remaining work was completed by C a...
A car running with a speed of 69 km/hr takes 28 hours to go from 'A' to 'B'. If on the way back from 'B' to 'A', the car takes 20% less time than it tak...
Four bells ring at 16, 24, 36, 42 minute intervals. If they ring together at 6.00 a.m., after how long would they next ring together?
...