The correct answer is E
Ashish and Anil can do a piece of work in 15 days and 25 days respectively. Ashish completed 40% of the work. Find the time taken by Anil to complete th...
Anita and Binita have individual completion times for a task; Anita can complete it in 40 days, while Binita can do it in 56 days. Anita initiated the t...
A is half as efficient as B. C does half as much work as A and B together. If c alone can do the work in 40 days. Then in how many days will A, B and C ...
Aaru Swati and Rajni can finish a work in 4 days if they work together. However, Aaru alone will take 9 days to complete the work, and Swati alone will ...
‘A’ alone can complete a work in 10 days. ‘B’ alone can complete the same work in 20 days. If ‘A’ and ‘B’ work together for 3 days, then...
Working in a shift of 5 hours 39 workers take 12 days to build a stretch of highway. In how many days will 30 workers working 6 hours a day, complete th...
A, B, and C can complete a job in 15, 20, and 30 days, respectively. They start the work together but after 3 days, A leaves. Then, B works alone for 5...
Virat can do a piece of work in 26 days and Sachin can do the same work in 39 days. If Virat works for 5 days and got Rs. 3000, and the remaining work w...
A contractor undertook to make 20 km of roadway in 48 weeks. In 28 weeks, 8 km was completed by 120 men working 12 hours a day. The men then agreed to w...
A and B together can complete a job in 2 days. A alone takes x + 6 days to complete the job, while B alone takes x + 24 days to complete the same job. <...